Building Progress Page 1

A 3d rendering Zach did before the building was even built

Architectural renderings
Building drawings by Remiker Architects


The vacant lot before construction started

07/16/2003...

Three years of paper work and now we finally get to move some dirt.
I couldn't have picked a more appropriate machine to make the first hole.



After some fine adjustments, they fired up the massive auger.
This picture captures the instant the ground was broken.





Here's Larry making sure everything is going well.




After the 26 foot deep hole was drilled, they carefully lowered the
elevator jack (the long white tube) into place.


This picture shows you how big this machine really is.




7/28/03...

Excavation has begun. Many truckloads of dirt will be remove to make room for the foundation and slab.





8/06/03...

We drilled 22 12-foot deep holes for concrete piers.



Unfortunately, we hit the neighbor's sewer line while digging one of the holes. Fortunately, my plumber could easily patch it and reroute it.




8/14/03...

What a fine elevator pit!



The first forms have gone up.





8/20/03...

The elevator pit floor has been poured



The rock and sand is in place and ready for the slab's rebar.




8/25/03...

Day of the big pour















8/29/03...








09/02/03...

The building is starting to take shape


Yes, there's more Jump to page... 1 , 2 , 3 , 4
 